|
From: Kae LeBeau [kae.lebeau@Seattle.Gov]
Sent: Friday, October 18, 2002 4:20 PM
Subject: Ravenna Creek Daylighting Alternate Choice
The following is a message from Parks and Recreation Superintendent
Ken Bounds about his Ravenna Creek Daylighting decision.
Dear Community Member:
After considerable thought about the Ravenna Creek Daylighting project,
I have directed the project team to proceed with design based on a
modified version of Alternative #1. Alternative # 1daylights the creek
as feasible around the existing ballfield. It stops short of reaching
the south edge of the park. I have directed the designer to modify
that option so that it will accommodate a potential future expansion
to the south if we relocate the ball field. This choice will result
in a considerable improvement to the creek, will not require expensive
retaining walls and removal of mature trees, and will provide maximum
flexibility for the future.
As you know, there was a strong community lobby in support of Alternative
#2, which was also the preferred alternative recommended by the Board
of Park Commissioners. Alternative #2 represents an effort to reach
a compromise between several site uses. It relocates the ballfield
on the lower site by building concrete retaining walls into the hillside.
The slight increase in creek length between this alternative and alternative
# 2 does not warrant the environmental impacts of concrete retaining
walls and the loss of several mature trees along the south edge of
the park. This design also splits the financial resources and the design
focus of the project by including the creation of a new ballfield.
I appreciate the environmental arguments for removing the baseball
field and re-grading the entire lower playfield in order to restore
the creek corridor. During the conceptual design phase, I directed
the project team to search for options to relocate the field. We considered
several alternate sites, and we examined the possibility of reprogramming
other ballfields to accommodate the existing Little League use. The
problem is that there are no readily available sites for a new field.
In addition, upcoming improvements to both Sand Point Magnuson and
Meadowbrook will require closing those fields for construction. Anything
we do to reprogram for Roosevelt, University and Greenwood (RUG) would
leave another existing group without a field. We will continue to face
a field shortage for the existing programming for several years. The
City made a commitment at the onset of this project to maintain the
existing athletic uses. As we cannot accommodate the existing uses
through reprogramming or relocating the field, removing it is not an
option.
A modified Alternative #1 maximizes the resources going to the creek
and does not spend resources on the expensive retaining walls associated
with relocation of the ballfield. By not moving the ballfield, right
field remains the shorter outfield, which is preferable to the Little
League. It also leaves open the opportunity to redirect the stream
in the south end of the Park at some time in the future if and when
we have additional ballfield capacity that meets league standards.
This was a difficult choice, and I appreciate the passion, the insight,
and the time so many of you contributed to the alternative selection
process. I have made my decision after consulting with the project
team and key community members. I look forward to completing project
design and construction. We will schedule a public meeting during the
design development phase to present the working drawings to the community.
I hope that you will continue to stay involved with us and enjoy the
improvements to Ravenna Creek. If you have any questions, please contact
Virginia Hassinger, Project Manager, at 233-7936.
Sincerely,
Kenneth R. Bounds
Superintendent
|